Camino Tassajara Shoulder Widening

Project Description
Federal No.:  HSIPL-5928 (105)
Project No.:
 0662-6R4131 

Project Description:
  The project includes pavement widening, fill slopes, drainage culvert modifications, rock slope protection, fencing, metal beam guard railing, signing and striping.

General Location:
On Camino Tassajara, beginning approximately 2,000 feet east Blackhawk Drive and ending approximately 100 feet south of the intersection with Finley Road        

Supervisory District: #3
Thomas Brothers Map Reference:  654 – E5, F5, F6
Contractor: Grade Tech, Inc. 
Resident Engineer: Chad Langstraat
Phone: (916) 509-1301
Start Construction Date: July 14, 2014
Working Days: 45
Estimated Completion Date: September 16, 2014