Project Information
Project No.: 0662-6R4051-14
Project Description:The work to be done generally consists of replacement of curb, gutter, and sidewalk to meet ADA standards; installation of street trees and irrigation system; and installation of planter pots.

General Location: El Sobrante
Supervisory District: 1
Thomas Brothers Map Reference: Thomas Bros. page 589/C-2
Contract Cost (Est.): $1,545,000
Project Manager: Rob Tavenier
Bid Due Date: August 5, 2014
Funding Source: TLC, Proposition 1B
Working Days: 105 working days
Construction Date: Fall 2014
Outreach Program: The bidder shall make a “Good Faith Effort”, and document this effort, to obtain sub-bid participation by MBE’s, WBE’s, OBE’s, SBE’s and LBE’s in accordance with the project special provisions to be eligible for award.  Bidders that have not attended a pre bid meeting in the last 12 months should attend the County pre bid meeting noted in the Notice to Contractors.  The pre bid meeting will include an overview of the Outreach Program requirements, and staff will be available to answer your questions.