2014 Discovery Bay Asphalt Rubber Cape Seal

Project Information

Project No.: 0662-6R4051-14

Project Description: The work to be done generally consists of applying an asphalt rubber chip seal covered with a type II slurry seal to approximately 208,590 square yards of roadway and a Type II slurry seal on an additional 98,759 square yards of roadway in the Discovery Bay area in east Contra Costa County. Work will also include surface preparation (Not including base failure repairs and crack sealing by others), striping removal, and placement of thermoplastic striping and pavement markings.

General Location: Roads within Discovery Bay west of Discovery Bay Blvd and Southwest portion of Discovery Bay west of Bixler Road
Supervisory District:
#3
Thomas Brothers Map Reference: 638/A4-A6
Contract Cost (est): $1,751,000
Project Manager: Henry Hussey
Bid Due Date: April 8, 2014
Funding Source: Local Road Funds
Working Days: 45
Construction Date:
June 2014

Outreach Program: The bidder shall make a “Good Faith Effort”, and document this effort, to obtain sub-bid participation by MBE’s, WBE’s, OBE’s, SBE’s and LBE’s in accordance with the project special provisions to be eligible for award.  Bidders that have not attended a pre bid meeting in the last 12 months should attend the County pre bid meeting noted in the Notice to Contractors.  The pre bid meeting will include an overview of the Outreach Program requirements, and staff will be available to answer your questions.