2014 Micro-Surfacing Project

Project Description
Project No.:  0672-6U2151-14       

Project Description:  The project consists of applying micro-surface treatment to arterial roadways: Richmond Parkway, Danville Boulevard, Treat Boulevard and streets in the Kensington area as shown on the plans. Work will also include surface preparation including base failure repairs (Crack sealing completed by others), tree trimming, striping removal, monument installation, and placement of thermoplastic striping and pavement markings.
                                                                
General Location: Kensington, Richmond, Alamo and Walnut Creek     
Supervisory District: 1, 2 and 4      
Thomas Brothers Map Reference:  609 F4, 612 D1, 632 D1-H7       
Contractor: Telfer Highway Technologies
Resident Engineer: Donna James               
Phone: (707) 704-4152
Start Construction Date: June 16, 2014
Working Days: 45
Estimated Completion Date: August 13, 2014