Countywide Overlay Project

Project Information
Project No.:  0662-6R4073             
Federal No.:  TBD

Project Description:  Provide pavement rehabilitation to three arterial roadway segments within Contra Costa County which includes Vasco Road, Byron Highway and Pleasant Hill Road.

General Location: Vasco Road- 2300’ south of Walnut Blvd. to Frisk Creek Bridge. Byron Highway- Brentwood Blvd. to 1200’ north of Marsh Creek Road. Pleasant Hill Road- 500’ north of Rancho View Drive to Crosswalk at Reliez   Valley Road.             
Supervisory District: # 3 & 4       
Thomas Brothers Map Reference:  Vasco Rd- 616/H7, TO 637/D7,               Byron Highway- 617//D4, D5, D6, Pleasant Hill Road- 611/H4, H3
Contract Cost (Est.): $2,500,000              
Project Manager: Brian Yip                       
Bid Due Date: TBD              
Funding Source: LSRP Federal Funds, local Road Funds 
Working Days: 40 working days            
Construction Date: 2015 beg construction
 
DBE Program: This project is partially funded by federal funds from U.S. Department of Transportation.  The prospective bidders are required to comply with 49 Code of Regulations (CFR) Part 26.  The prospective bidders must meet the project-specific Underutilized Disadvantaged Business Enterprise (UDBE) goal or document the Good Faith Effort (GFE) process.  It is important to note that to comply with the County DBE program’s Good Faith Effort, the bidders must take certain actions a minimum of 15 days prior to bid opening.

Project Links
  • Project Location Map
  • Notice to Contractors
  • Planroom
    • PS&E package
    • Bidders List
    • Q&A
  • Bid Results