Posted on: June 20, 2017

June 20: Update on PG&E Work along Morgan Territory Road

Early next week, PG&E will begin the work on Morgan Territory Road to safely relocate two electric poles damaged by the landslide. The work is planned over two days, Monday, June 26, and Tuesday, June 27, 2017.

Two additional 70 – 80 foot poles will be...

Read on...

Posted on: June 14, 2017

June 14: Culvert work to be rescheduled

County Public Works crews began repair work on the culvert on the south section of Morgan Territory Road today, but found that the ground is too saturated from winter rains to complete the repair work now. We’ll keep you informed when we are able to resch...

Read on...

Posted on: June 8, 2017

June 8: Culvert work scheduled for June 14-16

Culvert work on Morgan Territory Road is scheduled for June 14 through June 16 between 9:00 a.m. and 4:00 p.m. The work will occur approximately 8 miles south of the Morgan Territory Road temporary signal. Drivers can expect 30 minute delays and are encou...

Read on...

Posted on: June 2, 2017

June 2: Construction of temporary access road to begin the week of June 5

Temporary Access Road

The County awarded a contract to Graniterock Company on May 11, 2017 to install a gravel road extending from near the end of the private Leon Drive to the Marsh Creek Detention Facility driveway.   The gravel road will serve ...

Read on...

Posted on: June 1, 2017

June 1: AT&T working in the slide area today

AT&T will be working in the slide area today between 12pm and 5pm to raise their cable. They will have flaggers through the area to direct drivers.

Posted on: April 25, 2017

April 25: Morgan Territory Road Repair Project

At their meeting today, members of the Board of Supervisors authorized the Public Works Department to advertise the Morgan Territory Road repair project. Contractors will have four weeks to submit their construction cost bids. Four weeks is the minimum bi...

Read on...